Some of the functions of this process include describing the methods for executing the work of the project to fulfill the project objectives?

documenting dependencies and interactions among the processes, determining the validity of and maintaining the performance baselines, and determining key management reviews for pending decisions. Which of the following does this describe? Choose the best answer.

 A. The output of the process is the project scope management plan.

B. The project charter is an input of the process.

C. This process belongs to the Project Scope Management Knowledge Area.

D. The project scope management plan and quality management plan are two examples of the subsidiary plans contained in the output of the process.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/02
Soman Anandan
by Soman Anandan , Officer , National Commercial Bank

Implementing Business Process improvement

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

 Explanation: The Develop Project Management Plan involves describing the methods for executing the work of the project, documenting dependencies and interactions among the processes, determining the validity of and maintaining the performance baselines, and determining key management reviews for pending decisions, among other elements. The project scope management plan and quality management plans are examples of the subsidiary plans contained within the project management plan, which is the output of this process

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option C