his PMI certification and was subsequently fired. Unfortunately, he didn't create a project charter or a preliminary scope statement. You are ready to elaborate the deliverables and requirements of the project and know that you can use one of the following in place of the charter or preliminary scope statement. Which one can you use?
A. Expert judgment
B. Strategic plan
C. Product scope description
D. Business justification
C. Product scope description
The product scope description can be used as an input to the Scope Definition process when the project charter and/or preliminary project scope statement are missing.
MY Option will be -B - Strategic plan.
B.
Due to lack of project charter and project scope which must generate during the initial phaze. It is prefere to generate an Strategic Plan which will help to visualise project deliverables and requirements.
Thank you for the invitation
I agree the option B