Which logical relationship does the PDM use most often?

 A. Start-to-start

B. Start-to-finish

C. Finish-to-finish

D. Finish-to-start

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/17
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: Finish-to-start (FS) is the most commonly used logical relationship in PDM and most project management software packages.