Which of the following is true regarding the project charter?

 A. The project charter should be published under the project sponsor's name.

B. The project charter should be published under the name of the project manager.

C. The project charter should be published under the name of the project champion.

D. The project charter should be published under the name of a manager external to the project.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/17
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: According to the PMBOK Guide, the project charter should be published by a manager external to the project but with sufficient power and authority to carry it off.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option A