But your manager is forcing you to start the project right away. What is the BEST thing to do?
A. Start project right away.
B. Ask your manager to send approval email.
C. Start work on complex activities.
D. Do the impact analysis and show the impacts of start project without approval.
Answer: DExplanation: The best thing to do the impact analysis and show the impacts of start project without approval. This is the only choice that prevents future problems .