You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures?

as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Human Resource Planning B. Acquire Project Team C. Direct and Manage Project Execution D. Develop Project Team

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/28
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: The Acquire Project Team outputs include the project staff assignments, and the project team directory is part of this output.