A. To examine the work of the project and formally accept the work results B. To determine which project processes are inefficient or ineffective C. To improve processes and reduce the cost of quality D. To improve processes and increase the percentage of product or service acceptance
.A. To examine the work of the project and formally accept the work results
To improve process and increase the precetage of product and service acceptance
Answer: AExplanation: The acceptance of work results happens later during the Scope Verification process, not during Perform Quality Assurance.
All answers are correct after excluding number 1
To determine which project processes are inefficient or ineffective
Option A is correct answer
A. Examiner le travail du projet et accepter formellement les résultats du travail
Note :the pre-acceptance of quality auditor must be temporairement the final belong to the owner or "customer"