You are the project manager for Changing Tides video games. You have produced a project schedule network diagram and have updated the activity?

list. Which process have you just finished? A. The Activity Definition process, which identifies all the activity attributes B. The Activity Sequencing process, which identifies all the specific activities of the project

C. The Activity Sequencing process, which identifies all the activity dependencies D. The Activity Definition process, which diagrams project network time estimates

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/18
المصباح احمد
by المصباح احمد , منسق مشاريع ومدير مشتريات ومبيعات , ذرى الجزيرة

new positive action must be added

Aneesh Shandilya
by Aneesh Shandilya , Manager/ Lead Electrical , Orpic

The correct answer is option C.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: The Activity Sequencing process produces project schedule network diagrams, updates to the activity list, updates to the activity attributes, and requested changes. The purpose of this process is to identify all activity dependencies.