Register now or log in to join your professional community.
A. The level of effort of a task B. When a task starts and stops C. How tasks are related to each other D. Who is assigned to what task E. All of the above.
Option B - Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements constitute the work breakdown structure of the project.
Answer: BExplanation: Section: (none) Reference: Rita says that a Gantt chart in its purest form does not show task interdependencies. That would make B correct. (in second thought - According to PMBOK, Schedule development process - The Bar chart or Gantt chart, shows the durations, the starting and the ending date and sometimes the dependencies. So why would a and c not be an appropriate answer.)
Option B is the best choice.
adwjkhdkiauhksjdskdhbsmdnAd WDhjWD xhgAmsvcnmbdvsjhvszdjhzvdjzwhdvzjhdvzwdlkjhzvwdlhjzs cdkjdjkQWDjqdjqkdlqdmwewrrr