You are project manager and now in middle of creating RFP(Request for proposal). RFP(Request for proposal) is done in _?

 A. Plan Procurements B. Close Procurements C. Administer Procurements D. Conduct Procurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
Danish Sheikh Qureshi
by Danish Sheikh Qureshi , Manager-Projects , Adani Skill Development Centre

Answer Should be Plan Procurements

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the best choice.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: RFP(Request for proposal) is done in Plan Procurements process,