A. Determine Budget B. Estimate Costs C. Estimate Activity Durations D. Estimate Activity Resources
It will come under Cost Management Process so the option B. Estimate Cost is the correct option.
Option B is the correct choice.
Answer: BExplanation: The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. Management Contingency Reserve is identified in Estimate Costs process.