Register now or log in to join your professional community.
A. Updates to the cost management plan B. Budget updates C. Revised cost estimates D. Corrective action
B. Budget updates....................
Answer: BExplanation: Budget updates might require cost rebaselining .
Mises à jour du plan de gestion des coûts apres des mesures correctives
Option B is the correct choice.