Which organization, the project manager has total control of projects?

 A. Projectized organization B. Balanced Matrix organization C. Weak Matrix organization D. Strong Matrix

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Projectized organization: The project manager has total control of projects. Personnel are assigned and report to a project manager.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.