Which technique would you be using if you analyze which sequence of activities has the least amount of flexibility when you need to predict project?

  duration.

A. Critical path B. Dependency diagramming C. PERT D. Gantt chart E. Monte Carlo method

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/31
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Critical path -------------------

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.