Which of the following can be used to measure overall project performance?

 A. A work breakdown structure. B. A Gantt chart. C. An earned value chart. D. A PERT chart.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. An earned value chart -----------------