In which of the following situations would the PERT method be applied most?

 A. When little experience exists on which to base estimated of activity duration. B. When knowledge of the interrelationships of activities are crucial. C. When there is limited knowledge regarding the cost estimation related to the project. D. When resource requirements are well defined.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/21
Matthew Chukwumah  Ajuwa
by Matthew Chukwumah Ajuwa , Safety coordinator and Logistics , ALCON NIGERIA LTD(CONSTRUCTION) SHELL CONTRACTOR

B -when knowledge of the interrelationshipa activities are crucial

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. When little experience exists on which to base estimated of activity duration.