A. Pareto diagram. Statistical sampling. C. Performance measurement. D. Parametric modeling. E. All of the above
C. Performance measurement. ---------------
It depends sometimes on project requirements and company assets. But for sure, whenever applicable, performance measurements is the most useful during project schedule control stage.
E: All Of above
statistic sampling and performance measurement make quality assure and parametric modeling help me to complete project on time.
i would prefer Performance measurement technique, i helps in analysing information regarding the project and let us have full control over shedule.
Depends on the company
Statistical sampling of similiar Project if New
or
Performance measurement if i have samples