Which of the following options is irrelevant to the resource assignment matrix in project planning?

 A. The communication lines both within and outside the project. B. The authority to approve at various completion stages. C. The participant compensation level. D. The responsibility assignment to the work breakdown structure.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/07
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The participant compensation level.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the corect choice.