C. Financial records. -
Important items / equipments procured for a project, that should be listed in the "Inventory Schedule" with all the required informations as noted below and will be the part of "Operation & Maintenance Manual" while handing over the project to the end user;
1. Maufacturer & Suppliers contact information
2. Items Description, Make & Model
3. Spare parts & Part List Diagram for ease ordering the item, when it requires replacement