The authority to accept or reject a requested change in a large and complex project, should rest with _?

 A. The sponsor.B. The president. C. The change control board. D. The client. E. The project manager.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The change control board. ------