Where would you document a change that was approved when the change that involves the upgrade of certain material, is proposed halfway during the?

implementation of the project and will not result in a change in the cost or schedule? A. Project charter B. Execution phase C. Procurement Management plan D. Work breakdown structure E. Quality assurance plan

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2018/04/04
Muhammad Farooq
by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

C. Procurement Management plan