A. The project is estimated to be- days ahead of schedule. B. Two branches converge on a node. C. The critical path must be evaluated to determine actual slack time. D. Duration compression may be required to meet the original project scope. E. None of the above.
D. Duration compression may be required to meet the original project scope.