Question added by Zaid Alshufiyyen , Head of Energy Sector Section , Energy & Minerals Regulatory Commission
Date Posted: 2018/04/18
Deleted user
by Deleted user

Try with power factor correction!

ersen akdeniz
by ersen akdeniz , Chief Electrical Engineer , Borusan ENBW Energy Investments

if the point of common coupling is weak in terms of SC-MVA capacity, further transmission system investment is required for safe/reliable/stable operation

Deleted user
by Deleted user

Diversity and wide geografical distribution of renewable sources can be a solution.