in the event that a problem does arise, they will work overtime to stay on schedule. How would you react as the project manager operating in a matrix organization? A. Assess the cost implication of this activity in the implementation phase. B. Request that the IT department's commitment be in writing. C. Assess the risk of this activity and develop a response strategy. D. Note this information in the minutes of the conference report meeting. E. Request that the IT department delay implementation of the CRM application system until your project is completed.
C. Assess the risk of this activity and develop a response strategy.