Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Prior to heavy lifting, what is the most critical point concerned?

user-image
Question added by MANOJ KUNJAPPY , Senior Document Controller , Samsung Engineering Co. Ltd.
Date Posted: 2013/05/14
Mammdouh Krdi
by Mammdouh Krdi , project manager , AL Muntasser

prior heavy lifting need checking the weight befor taking a decision what the kind of lifting machine to use andthe minimum radius avialable and compar that with lifting machine radius with safty times

Deleted user
by Deleted user

Prior heavy lifting operation ensure;

You carryout a full risk assessment which include but not limited to the following; 

1/ The machine is certified to lift and shift the item

2/ The machine can and will handle the weight of the item

3/ There is a free access to site

4/ The site is free of obstacles (overhead cables, towers, bridges etc..) which may prevent the lift  

5/ The receiving platform is able to take the weight 

6/ Banksman is a must.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.