Pareto Analysis, cause and effect diagrams and flow charts are used in quality. A. Control. B. Assurances. C. Planning. D. Verification?

user-image
Question added by Richa Tiwari , Quantity Surveyor , Space Contracting Limited
Date Posted: 2018/05/24
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

In the light of PMI PMBOK it Pareto Analysis related to qualityy control.

Richa Tiwari
by Richa Tiwari , Quantity Surveyor , Space Contracting Limited

Pareto Analysis, cause and effect diagrams and flow charts are used in quality Control