A. By project phase or project deliverable B. By risk or quality metric C. By product feature or unit of work D. By charge code or initial estimate
ma réponse est que la meilleure façon de procéder à un découpage de travaux est de considerer les phases du projet ou ses livrabes.
Answer: AExplanation: The WBS work packages can be displayed by project phase or by project deliverable. It depends on how your company needs to see the work organized. If you use the same phased lifecycle for all projects, it can be easier to show all of the work as it breaks down within each phase. If you have various teams depending on the deliverables your team will produce, it can make sense to break the work down by project deliverable.