A project manager on a construction project includes a line item in the budget for insurance for the equipment and job site. This is an example of:?

A. Acceptance B. Transference C. Avoidance D. Mitigation

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/06/06
Sherif Shabaan
by Sherif Shabaan , Green Riyadh.. Site Civil Engineer , Al Fahd Company

  ................ B. Transference

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: One effective way to deal with a risk is to pay someone else to accept it for you. This is called transference. The most common way to do this is to buy insurance.