Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated ?

enough time for some of the technical work they needed to do. She requested that the new work be added to the scope statement and that the time to do the work be added to the schedule. The change control board approved her change. What's her next step? A. Update the scope and schedule baselines to react the approved change. B. Gather performance metrics on the team's work so far. C. Start doing the work D. Perform Quality Assurance

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/06/06
Niranjan Bokil
by Niranjan Bokil , Head-Operations , Signode India Ltd

Brandi needs to update the scope and scheudle baseline.

Rahul Nutalapati
by Rahul Nutalapati , Freelance Photographer , Infinite stories

A. Update the scope and schedule baselines to react the approved change.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: When a change has been approved you always need to update the baseline and then implement the change. That way, you will be sure to track your performance versus new scope and schedule expectations and not the old ones.

More Questions Like This