Register now or log in to join your professional community.
Which contract type is MOST appropriate for this project? A. Time and Materials (T&M) B. Fixed price (FP) C. Cost plus percentage of costs (CPPC) D. Cost plus fixed fee (CPFF)
A)Time and materials
The project manager and the contractor shall have access to the texts of the agreement (contract of work) between the statement of the main issues that involve the work force, including: Duration of the project Cost of materials Contract Value Contracts of both teams
Answer: A
Explanation: Time and Materials (T&M) contracts are used in labor contracts. In a T&M contract, the seller pays a rate for each of the people working on the team plus their material costs. The "Time" part means that the buyer pays a fixed rate for labor - usually a certain number of dollars per hour. And the "Materials" part means that the buyer also pays for materials, equipment, office space, administrative overhead costs, and anything else that has to be paid for.