You put the requested changes through change control and they are approved so you need to update the Scope Statement to include the new work. Where can you find the most updated version of the Scope Statement? A. In the Document Repository B. In the Communications Management Plan C. In the Configuration Management System D. In the Project Management Plan
Answer: CExplanation: The configuration management system is there to be sure that everybody on the team has the most updated version of all of the project documents. Whenever a project document is changed, it is checked into the Configuration Management System so that everyone knows where to go to get the right one.
C. in the configuration management system