What is the BEST way to make an accurate forecasting of ETC? Manual Forecasting of cost of remaining work. BAC – EV (BAC – EV)/CPI EAC - AC

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2018/06/23
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

As per PMBOK6, it is the manual forecasting of the cost of remaining work.

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

Manual Forecasting of cost of remaining work.