Which of the following is NOT an example of a deliverable?

A. Parametric Estimation B. Work Breakdown Structure C. Project Schedule D. Project Management Plan

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/06/27
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Parametric estimation is a tool for creating estimates. It's not a deliverable.