The process of Conduct Procurements is part of which phase? 1. Planning 2. Execution 3. Control 4. Closure

user-image
Question added by Richa Tiwari , Quantity Surveyor , Space Contracting Limited
Date Posted: 2018/07/11
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

It is part of Execution.....

Richa Tiwari
by Richa Tiwari , Quantity Surveyor , Space Contracting Limited

Conduct Procurements is part of execution phase.