Register now or log in to join your professional community.
all of your response strategies. What kind of risk is this and what should you do about it? A. It's a residual risk. You don't need to plan a response strategy for it because you've already implemented all of the risk responses you can plan for. B. It's a secondary risk. You don't need to worry about it. C. It's a contingency reserve. You should only use it if the first risk occurs. D. It's a residual risk. You need to plan a response strategy for it.
A . It's a residual risk. You don't need to plan a response strategy for it because you've already implemented all of the risk responses you can plan for.
Answer: AExplanation: Residual risks are risks that remain even after you have planned for and implemented all of your risk response strategies. They don't need any further analysis because you have already planned the most complete response strategy you know in dealing with the risk that came before them.
hi
iam hamid from iran.
can you guide me How can i work in qatar.?
sooooorrrrrrrrrrry
Its depends about the status of this risk, if the risk extremely dangerous, that's mean it's no wait's for another meetings and I should make another immediately meeting to discous about what I discoverd, and if the risk is not dangerous, I will put a note for myself to be in discousion at another closely meeting.