The project charter is typically approved by the project sponsor, although some charters can be approved by key stakeholders instead.?

Which of the following BEST describes the role of the project sponsor on the project? A. The sponsor verifies that all of the work was completed B. The sponsor negotiates all contracts C. The sponsor provides funding for the project D. The sponsor manages the project

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/07/11
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The project sponsor is the person (or people) that pays for the project. Sometimes this means the sponsor directly provides funding; other times, it means the sponsor is the person who signs the organizational approval to assign resources. Either way, you can usually tell who the sponsor is by finding the person who can approve or deny the budget.