Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

When do you perform stakeholder analysis?

A. When putting changes through change control B. When defining the project scope C. When developing the project charter D. When creating the project management plan

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/07/18
Syed Saifur Rahman
by Syed Saifur Rahman , Assistant Vice President , Computer Network Systems Limited, Bangladesh

D. When creating the project management plan

Ruslan Nurmanov
by Ruslan Nurmanov , Various Business development / Continuous improvement projects , Various projects

Based on ABPMP definitions I would prefer systematic analysis throughout the project life cycle but the most important would be during the PM plan. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B

Explanation: Stakeholder Analysis is one of the tools and techniques of the Scope Definition process. And that shouldn't really be a surprise. After all, the goal of stakeholder analysis is to write down the needs of your stakeholders. And when is it most important to figure out what your stakeholders need? When you're defining the scope of the project work!

More Questions Like This