Which of the following is NOT an input to Perform Quality Control?

A. Recommended Defect Repairs B. Checklists C. Deliverables D. Work Performance Information

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/07/26
Muhammad Usman Saleem
by Muhammad Usman Saleem , Internal Audit Manager , The Punjab Aluminum

Recommended Defect Repairs is not an input to perform quality control.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Explanation: The most important part of the Perform Quality Control process is that your team has to inspect each deliverable in order to verify that it meets its requirements. So what do you need to do that? Well, obviously you need the deliverables! And checklists are really useful too, because they help you inspect each deliverable. You need work performance information, because that tells you how well the team is doing the job. But Recommended Defect Repairs aren't an input - they're the output