Register now or log in to join your professional community.
A. Direct and Manage Project Execution B. Develop Project Management Plan C. Integrated Change Control D. Monitor and Control Project Work
Answer: AExplanation: Changes are found in Monitor and Control Project Work, they are approved in Integrated Change Control and implemented in Direct and Manage Project Execution. When you are monitoring and controlling the project work, you are always looking for changes that might need to be made to your plan and assessing their impact. Then you present those changes to the change control board for approval. If they approve, you implement them in the Direct and Manage Project Execution process - that's where all the work gets done.