A. It formally assigns the project manager B. Includes a high level milestone schedule C. It is always created by the project manager D. It contains external constraints and assumptions
Project Charter is not necessarily be done by the Project Manager but it identifies the level of authority of the Project Manager.
Answer: CExplanation: The Project Charter is often created without the project manager's involvement. Sometimes it is handed to the Project Manager by the sponsor or high level manager.