You're managing an industrial design project. Your project is currently in the Initiating phase. The project charter has been created?

and you are working on developing the preliminary scope statement. Which of the following is NOT something that you should do? A. Create the change control system B. Identify internal and external constraints C. Document initial project risks D. Write down any assumptions that you have made

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/08/15
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: An important part of initiating the project is identifying any constraints on the project, creating a list of initial project risks, and documenting assumptions that you've made so far. If you do this, it will make it much easier to plan your project later on. However, you don't create the change control system in the Initiating phase - that's something that you do as part of your project planning activities.