Which of the following shows roles and responsibilities on your project?

A. Resource histogram B. Bar chart C. RACI matrix D. Human Resource Management Plan

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2018/08/15
Muhammad Farooq
by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Explanation: The RACI matrix shows roles and responsibilities on your project. RACI stands for Responsible, Accountable, Consult, Inform. Some people on your project will be responsible for activities, others might be accountable for them. The RACI matrix is a table that shows people and how they relate to the work that is being done. .