Register now or log in to join your professional community.
A. Write up a change request. B. Tell your team that the process has already been decided and they should follow it. C. Analyze the change versus the Project Management plan to see what its impact will be. D. Implement the change.
Answer: CExplanation: You may get a question on the exam that asks what to do when you encounter a change. You always begin dealing with change by consulting the project management plan.
Thank you for the invitation
Agreed with your Answer
With greetings and appreciation