Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders ?

to define the scope. The sponsors mentioned that the gazebo is a really important part of their daughter's wedding ceremony that was planned for7 months from then. In fact, they said that if the gazebo couldn't be completed in7 months, it wouldn't be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section of the document did the deadline appear? A. Project Deliverables B. Project Objectives C. Project Constraints D. Project Assumptions

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/09/05
Deleted user
by Deleted user

Thanks for invite Mr.Farook -

I agree with your answer - Important explanation   !!!

 

Regards * 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: Since the project absolutely must be completed in 7 months for it to be worth doing, the deadline is a constraint. It must be met for the project to be considered successful.