Register now or log in to join your professional community.
A. It describes the initial scope of the work B. It contains a list of all activities to be performed C. It identifies the sponsor and describes his or her role on the project D. It authorizes the project manager to work on the project
D
Explanation: The project charter does several important things: it lays out the project requirements, describes an initial summary milestone schedule, documents the business case and identifies initial risks, assumptions and constraints. But the most important thing that a project charter does is that it identifies the project manager, and assigns him or her the authority necessary to get the job done.