Register now or log in to join your professional community.
She assesses the impact of the change and tells the client how much time and money it will cost. But the client says that he doesn't have the time or budget to allow the change. What's the BEST way for Rekha to handle this situation? A. Hold a meeting with the client to figure out why he's asking for the change B. Have the client find more money for the budget C. Do nothing; she's the project manager, so she sets the rules D. Have her senior managers meet with the client to explain the situation
Answer: AExplanation: This project is not in good shape. The client has needs that aren't being met, but there may not be enough time or money to meet them. What's the project manager going to do? Well, the first thing that you should do any time you have a problem is try to figure out what's causing it. All of the other answers involved taking some sort of action, and you should never take action until you've figured out the root cause of the problem.