During which process is the Cost baseline developed?

A. Integrated change control B. Schedule development C. Cost budgeting D. Cost estimating

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/11/07
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Cost budgeting -------------------