Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are running a major project with four sub-projects. Each of the sub-project managers has developed a risk management plan, ?

identified many risks, analyzed them and planned for risk response. It is now two months later. What should you not do? A. Ensure that they handle all risks to save you from project level risk monitoring and control. B. Make sure that the sub project managers monitor their project work for new and changing risks. C. Make sure that the sub project managers keep track of the identified risks and those on thewatchlist. D. Make sure that the sub-project managers monitor trigger conditions for contingency plans.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/11/14
RICHARD GYANE SOMUAH
by RICHARD GYANE SOMUAH , office administrator , Presbyterian Church of Ghana

 Make sure that the sub project managers keep track of the identified risks and those on thewatchlist

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Ensure that they handle all risks to save you from project level risk monitoring and control.

More Questions Like This