Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In which of the following processes in the initial process group is one responsible for producing a high-level definition of the project?

and documenting the project requirements, deliverables and method of acceptance? A. Scope planning B. Develop preliminary project scope statement C. Develop project management plan D. Create WBS E. Develop project charter

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/12/19
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Develop preliminary project scope statement

More Questions Like This