Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A project manager is reviewing the scope of the project and the scope baseline of the project. This includes which of the following?

a. The original project schedule, budget, and scope b. The original project description and project charter c. The original scope of the project plus or minus any scope changes d. The current budget of the project

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2018/12/26
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

The original scope of the project plus or minus any scope changes during the execution of work.

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

ANS C - The original scope of the project plus or minus any scope changes.

More Questions Like This